Ferriere Nord Spa – Osoppo (Ud), Italy

TECHNICAL DATA

Year of execution 2011
Pre-shutdown works Civil Engineering
Pre-assembled blocks kg 40,000
Rebar Positioning kg 111,000
Formworks m² 1,600
Shut down period 7 calendar days
Demolition m³ 1,200
Excavations m³ 400
Structural blocks positioning kg 40,000
Structural pouring m³ 850
Rebar completion kg 5,000
Formworks completion m² 100