Acciaieria Arvedi – Cremona (Cr), Italy

TECHNICAL DATA

Project Revamping of EAF and changes of vertical structure of transfer car
Year of execution 2015
Civil Engineering Ferretti International Srl
Pre-shutdown works: 4 days (1 day for each weekly shutdown)
Core drillings for crossing diamond wire m 60
Shut down period 8 calendar days
Demolition m³ 60
Cuts by diamonds wire m² 70
Formworks m² 130
Reinforced Concrete m³ 70
Reinforced Steel Bars kg 5,000
Embedded Steel kg 2,000
Steel Structures kg 6,000