Ferretti International

Credits - Industrial Works

Lucchini Siderurgica Spa

Civil Works
Blast Furnace No. 4 Revamping
Piombino Plant - Italy

TECHNICAL DATA

Customer Lucchini Siderurgica Spa
Engineering Company Hoogovens
Civil Engineering Ferretti International Srl
Demolition of existing foundations m³ 2.500
Reinforced concrete m³ 4.800
Formworks m² 14.000
Reinforcement steel kg 390.000
Embedded steel kg 30.000
Work schedule 90 days